Westcoast Energy Inc.

Critical Notice

Physical Operations - Field Services

 

Notice:

 #100035

Revision: 

 #0

 

Subject:

McMahon Gas Plant August 7th, Outage Update

 

Summary:

McMahon Gas Plant Outage Update as of August 7th, 2019

 

 

McMahon Gas Plant Shippers and Producers
                                                                                                            
 

Date of Notice
August 8th, 2019
 
 
Facility/Pipeline:
McMahon Gas Plant
 
 
Within Zone:
Two (2)
 
Explanation:
 
 
 
 
 
Enbridge McMahon Plant is progressing through the repairs as planned and continues to be on schedule to start taking gas August 12th, 2019 and full service Tuesday, August 13, 2019.
 
Further updates will be provided on Friday, August 9th.
 
 
Status Communications:
 For more information, please contact your Strategic Account Specialist in Calgary, Alberta, Canada

 

 
Posting Date: 08-Aug-2019 09:43 CCT
Effective Date: 08-Aug-2019
End Date: 13-Aug-2019
Response Date: N/A
Location: Calgary
Contacts: CSR